Write-off of the Calin meter installation labour (31 Mar 2026)

Write-off of the Calin meter installation labour (31 Mar 2026)

Decided and booked 30 Oct 2026. UGX 2,001,841.38 of Green Volta labour for installing the Calin meters came off Sezibwa Phase 1 as at 31 Mar 2026, when those meters were replaced. FY2025-26 expense rose by 1,701,290.95, and FY2026-27 depreciation falls by 340,258.19. This follows on from decision 4 on the migration decisions page.

Why

The numbers

UGX, Sezibwa cost centre.

Before After Change
Phase 1 cost in 1711 11,885,613.34 9,883,771.96 −2,001,841.38
FY26 depreciation, Phase 1 (30 Sep 2025–30 Jun 2026) 1,784,470.17 1,483,919.74 −300,550.43
FY26 depreciation, Calin labour (30 Sep 2025–31 Mar 2026) – 200,732.59 +200,732.59
Loss on disposal, 31 Mar 2026 (5222) – 1,801,108.79 +1,801,108.79
Total FY26 expense 1,784,470.17 3,485,761.12 +1,701,290.95
FY27 depreciation, 30 Jun 2027 2,020,228.63 1,679,970.44 −340,258.19

Depreciation is 20% a year on the reducing balance (Microgrid Equipment, URA Class 3), with days counted inclusively, the same way ERPNext's schedule works. No cash moved.

What was booked in ERPNext

Step Record UGX
Phase 1's original FY26 depreciation cancelled ACC-JV-2026-00156 1,784,470.17
Phase 1 re-issued without the labour ACC-ASS-2026-00001-1 9,883,771.96
Calin labour as its own record, scrapped 31 Mar 2026 ACC-ASS-2026-00005 2,001,841.38
Depreciation to 31 Mar 2026 (5203) ACC-JV-2026-00157 200,732.59
Loss on disposal (5222) ACC-JV-2026-00158 1,801,108.79
Phase 1 depreciation, 30 Jun 2026 posts on the nightly run of 31 Oct 1,483,919.74

Accountant's answers (30 Oct 2026)

Approval

Reviewed by Aaron Tushabe. Approved by Hillary Arinda, as relayed by Aaron on 30 Oct 2026. Hillary: please confirm with a comment on this page so your sign-off is on record.


Revision #1
Created 2026-10-29 21:24:55 UTC by aaron.tushabe
Updated 2026-10-29 21:24:55 UTC by aaron.tushabe