NFE Commercial RPM Finance Glossary
Commercial RPM Finance & Energy Glossary
Plain-English reference for NFE commercial microgrid discussions
|
STATUS |
VERSION |
DATE |
|
How to use this glossary |
1. Core product and engineering terms
|
Acronym |
Stands for |
Plain-English meaning |
|
RPM |
Reliable Power Microgrid |
NFE's product model for providing reliable electricity as a service, with NFE owning/operating the enabling infrastructure during the service term and an optional later ownership path. |
|
EaaS |
Energy as a Service |
A commercial model in which the customer buys an energy service (for NFE, metered electricity and reliability) rather than buying the underlying solar, battery and inverter equipment. |
|
C&I |
Commercial and Industrial |
Customer segment covering businesses and institutions such as offices, schools, hotels, clinics, supermarkets, churches and factories. |
|
CAPEX |
Capital Expenditure |
Upfront investment in long-lived assets: batteries, inverters, PV modules, switchgear, cabling, controls, installation and commissioning. |
|
OPEX |
Operating Expenditure |
Recurring costs of running the RPM after construction, such as monitoring, service visits, insurance, communications, billing/admin and some maintenance. |
|
O&M |
Operations and Maintenance |
Activities needed to keep the system safe and performing: monitoring, inspections, cleaning where applicable, repairs, warranty administration and maintenance. |
|
EPC |
Engineering, Procurement and Construction |
The party/scope responsible for final engineering, purchasing equipment, constructing/ installing the system and commissioning it. |
|
BoS |
Balance of System |
All supporting equipment beyond the main PV modules/batteries/inverters: mounting, cabling, protection, switchgear, combiner boxes, earthing and related hardware. |
|
PV |
Photovoltaic |
Solar-electric generation technology that converts sunlight directly to electricity. |
|
BESS |
Battery Energy Storage System |
The complete battery system, including cells/modules and associated controls/safety systems. Often used interchangeably with “battery storage” at project level. |
|
LFP |
Lithium Iron Phosphate |
Lithium-ion battery chemistry commonly used in stationary storage because of its cycle life, thermal characteristics and cost profile. |
|
kW |
kilowatt |
A unit of power: the instantaneous rate at which electricity is being produced or consumed. Inverter size and maximum facility demand are power quantities. |
|
kWh |
kilowatt-hour |
A unit of energy: one kilowatt used for one hour. Customer bills and battery energy capacity are expressed in kWh. |
|
kWp |
kilowatt-peak |
The rated DC output capacity of a PV array under standard test conditions. |
|
DoD |
Depth of Discharge |
The percentage of a battery's nominal capacity that is used before recharging. A 90% DoD on a 120 kWh battery implies up to roughly 108 kWh discharged before other conversion losses/reserves. |
|
RTE |
Round-Trip Efficiency |
The ratio of energy recovered from storage to energy put into it. If 100 kWh charges a battery and 90 kWh is later delivered, RTE is 90%. |
|
EMS |
Energy Management System |
Software/control layer that decides how grid, PV, batteries and other resources operate, and provides monitoring, alarms, data and dispatch logic. For NFE this is part of the Microgrid OS. |
|
TOU |
Time of Use |
A tariff structure in which electricity prices differ by time period, such as peak, shoulder and off-peak. TOU pricing can make stored solar particularly valuable during expensive evening hours. |
|
SLA |
Service Level Agreement |
Contractual definition of the service NFE promises, such as availability, supported critical load, response time or outage-coverage duration. |
|
PPA |
Power Purchase Agreement |
A contract under which one party sells electricity to another under agreed pricing and terms. RPM is broader than a conventional PPA because reliability, storage and operations are central to the service. |
|
SPV |
Special Purpose Vehicle |
A separate legal entity created to own one project or a portfolio of projects. An RPM SPV could hold the equipment, customer contracts, debt and project cash flows separately from NFE's general corporate balance sheet. |
2. Project-finance terms
|
Acronym / term |
Stands for |
Plain-English meaning |
|
CFADS |
Cash Flow Available for Debt Service |
Cash generated by the project that is available to pay principal and interest after defined operating costs. In the current NFE screening model we conservatively calculate CFADS after routine O&M, NFE site overhead and lifecycle reserve contributions, but before debt service. |
|
DSCR |
Debt Service Coverage Ratio |
CFADS divided by scheduled principal + interest for the same period. Example: UGX 24.5m CFADS / UGX 13.9m debt service = about 1.76x. Above 1.0x means modeled cash flow exceeds scheduled debt service; lenders normally require additional cushion. |
|
DSRA |
Debt Service Reserve Account |
Cash reserve maintained to cover debt service if operating cash flow is temporarily insufficient. A 6-month DSRA holds roughly half a year of scheduled debt service. |
|
IRR |
Internal Rate of Return |
The discount rate at which the net present value of an investment's projected cash flows equals zero. In plain English, it is a time-adjusted measure of the return generated by investing capital today and receiving future cash flows. Compare IRR with NFE/investor return requirements and the risks in the assumptions; it is not the same as annual profit margin. |
|
Project IRR |
Project / unlevered Internal Rate of Return |
IRR calculated on the project's operating cash flows before debt financing. It answers: “Does the asset itself generate an adequate return regardless of how we finance it?” |
|
Equity IRR |
Equity Internal Rate of Return |
IRR on the cash invested by NFE/equity investors after accounting for debt drawdown and debt service. Leverage can increase or decrease equity IRR depending on the cost and terms of debt relative to project returns. |
|
NPV |
Net Present Value |
Today's value of future project cash flows after discounting them at a chosen required return. Positive NPV means the modeled project creates value above that required return; negative NPV means it does not. |
|
ROI |
Return on Investment |
A simpler return metric comparing gain to amount invested. Unlike IRR, basic ROI does not inherently account for when cash flows occur. |
|
WACC |
Weighted Average Cost of Capital |
The blended required return/cost of a project's debt and equity capital, weighted by how much of each is used. It is often used as a discount rate or hurdle reference. |
|
LLCR |
Loan Life Coverage Ratio |
Present value of CFADS available during the remaining loan life divided by outstanding debt. It looks beyond a single year's DSCR to the debt coverage over the loan period. |
|
PLCR |
Project Life Coverage Ratio |
Present value of CFADS over the remaining project life divided by outstanding debt. It includes cash flows after the loan matures and is therefore normally higher than LLCR. |
|
LCOE |
Levelized Cost of Energy |
Lifetime cost of producing electricity divided by lifetime electricity produced, discounted over time. Useful for comparing generation technologies, but it does not by itself capture reliability value or the timing value of stored energy. |
|
LCOS |
Levelized Cost of Storage |
Lifetime cost of operating storage divided by the energy delivered from storage, generally accounting for efficiency, degradation and replacement. It is a storage analogue to LCOE. |
|
P50 / P90 |
Probability-based energy cases |
P50 is the energy estimate expected to be exceeded roughly 50% of the time; P90 is a more conservative estimate expected to be exceeded roughly 90% of the time. Lenders often care about conservative production cases. |
3. Non-acronym terms that matter for RPM
|
Term |
Meaning for NFE |
|
Utility-price anchor |
NFE's customer price is tied to the applicable utility tariff or a defined utility-based index, rather than an equipment lease payment. |
|
RPM margin per kWh |
The value NFE creates inside the customer's energy price after accounting for the cost of grid/other energy and RPM operating provisions. It is not automatically an extra charge above the utility tariff. |
|
Lifecycle reserve |
Cash set aside over time to fund major replacements such as batteries and inverters. It prevents the model from looking profitable only because future replacement costs were ignored. |
|
Minimum energy commitment |
A contractual floor on energy purchases that can reduce lender volume risk. NFE may prefer not to use a hard minimum unless financing requires it, to preserve the “pay for what you use” proposition. |
|
Take-or-pay |
A stronger form of volume commitment under which a customer pays for a minimum contracted quantity even if it does not consume it. This can improve bankability but may conflict with the desired RPM customer experience. |
|
Early termination payment |
A payment due if a customer voluntarily exits before the contract ends, typically designed to cover outstanding debt, demobilization and a defined portion of unrecovered investment. |
|
Tariff indexation |
Rules that change the customer tariff over time based on a reference such as the applicable utility tariff, inflation or another agreed index. |
|
Critical load |
The subset of facility demand that must remain powered during an outage. Defining critical load can materially reduce battery/inverter size and project cost. |
|
Bankability |
The combination of predictable cash flows, enforceable contracts, acceptable risks, sufficient coverage, credible counterparties and technical/regulatory certainty that makes a lender willing to finance a project. |
4. The four numbers to remember in an RPM financing discussion
|
Number |
Question it answers |
|
IRR |
Is the project/equity return high enough for the risk and capital being committed? |
|
DSCR |
Does current project cash flow comfortably cover this period's debt payment? |
|
CFADS |
How much cash is actually available to service the debt after operating obligations? |
|
CAPEX per site / per supported kW |
How much capital must NFE deploy to deliver the promised reliability and what size portfolio can available capital support? |
|
Practical rule |
https://bookstack.nearlyfreeenergy.com/books/business/page/nfe-commercial-rpm-finance-glossaryGlossary