Sezibwa rooftop solar: panel layout and installer brief
For: the Green Volta installers and the NFE site team. Owner: Aaron Tushabe. Last reviewed: 21 Oct 2026. Status: proposed. The layout was worked out from satellite imagery, so do the site checks below before drilling.
The plan
- What: 8 × Golden Sun GS600N-144M (600 W, 2278 × 1134 mm, 30 kg each), 4.8 kWp in total, from the Muden quote.
- Where: the long north-west-facing face of the house at about 0.36236, 32.53602 (Nansana). The pin 0.36245, 32.53592 lands on the neighbour's roof about 15 m to the north-west.
- How: one row in portrait (long side up the slope), split into two groups of 4 with a 1.5 m gap around a vent or flue. The top edge sits about 0.4 m below the ridge. Flush-mounted at the roof pitch.
- Wiring: all 8 panels in one series string into PV1 of the SRNE ASP48120SH3. PV2 stays free.
Why this roof face
At 0.36° N the sun is close to overhead all year, so the direction a face points makes little difference:
| Roof face | kWh per year | Worst month (kWh/day) |
|---|---|---|
| North-west (chosen) | 6,780 | 16.8 (Nov) |
| South-west | 6,770 | |
| South-east | 6,660 | 15.7 (Jun) |
| North-east | 6,640 |
PVGIS (SARAH3 data, 2005 to 2023), 20° pitch, 14% system losses, no tree shade.
The trees decide it. Tall trees stand against the north, north-east and east sides of the house, and big trees to the south and south-west. The north-west face looks away from most of them. All 8 panels are on one string, so shade on one panel pulls down all 8. The north-west face also gives the steadiest output through the year.
Site checks before drilling
- Vent or flue. Satellite shows two dark marks about halfway along the face, roughly 8.7 m from the north-east end. If nothing is there, close the gap between the groups to about 0.3 m (keep the two rail pairs separate) and centre all 8 panels on the face.
- Pitch. Measure it and write it on this page. Anything from 10° to 25° is fine.
- Face depth. Eave to ridge along the slope must be at least 3.0 m (2.28 m panel, 0.4 m at the ridge, margin at the gutter). The satellite estimate is about 4.7 m.
- Purlins. Find their positions and spacing. Each rail has to sit on a purlin line.
- Shade.
- Stand at the array position at about 8 am, noon and 4 pm, or use a sun-path app.
- Trim the trees on the north, north-east and east sides and on the south and south-west sides to below ridge height.
- Check that the neighbour's roof (north-west, across the alley) is not higher than our ridge.
- Roof condition. Replace rusty or loose sheets and rotten timber under the array first.
- Cable route. Measure from the drop point to the inverter so the 6 mm² cable can be ordered.
Mounting
The hardware on the Muden quote matches this layout exactly: two 5.1 m rails per group of 4 portrait panels.
| Item | Per group | Total | On the quote |
|---|---|---|---|
| Rail, 5100 mm | 2 | 4 | 4 |
| End clamp | 4 | 8 | 8 |
| Inter clamp | 6 | 12 | 12 |
| L-foot | 6 | 12 | 12 |
- Rail position: rails run parallel to the ridge, about a quarter of the panel length (about 570 mm) in from the top and bottom edges, so about 1.14 m apart.
- The panel datasheet does not give the clamping zone, so check Golden Sun's installation manual.
- Move the rails within that zone so they land on purlins.
- L-feet: 3 per 5.1 m rail gives spans of about 2.25 m. Check the rail's span table. 4 per rail (about 1.5 m spans) is safer: that's 4 more L-feet, about 48,000 UGX at the quoted price.
- Fixing: fix the L-feet into the purlins, not just the iron sheet. Go through the crest of the corrugation, with EPDM washers and sealant.
- Airflow: leave about 100 mm under the panels. Cooler panels produce more.
- Load: about 240 kg of panels plus rails, spread over about 21 m².
Wiring: one string of 8 into PV1
| String of 8 | SRNE ASP48120SH3, per PV input | OK | |
|---|---|---|---|
| Open-circuit voltage | 422 V at 25 °C, about 440 V on a cold morning | 800 V max | ✓ |
| Max-power voltage | 359 V, about 310 V on a hot afternoon | 200 to 650 V tracking range | ✓ |
| Current | 13.4 A at max power, 14.0 A short-circuit | 22 A max | ✓ |
| Power | 4.8 kW | 9 kW max | ✓ |
The hot and cold figures assume typical n-type temperature coefficients (open-circuit voltage −0.27 %/°C, max-power voltage −0.30 %/°C), because the panel datasheet does not give them.
- Two strings of 4 will not work. They would run at about 155 to 180 V, below the inverter's 200 V minimum. The 4 + 4 split is physical only.
- Panel to panel: panels 1 to 4 connect directly with their 300 mm leads. A short jumper crosses the gap to panel 5, then panels 5 to 8 connect directly.
- Return lead: the string's + leaves panel 1 and its − leaves panel 8, so one lead runs back along the row (about 11 m).
- Tie it under the panels along the lower rail.
- Drop both leads at whichever end is nearer the inverter.
- Keep + and − together all the way to the inverter. A small loop picks up less lightning surge.
- Cable: 6 mm² UV-rated PV cable (the 4 mm² was out of stock). Voltage loss over a 30 m run is under 1%.
- MC4 connectors: crimp them with the proper tool and mate only with compatible connectors.
- At the inverter:
- The 32 A 4-pole DC isolator, wired to its diagram for 500 V+ DC (usually two poles in series on each polarity).
- Then the 1000 V DC surge protector, with a short lead to earth.
- The inverter is IP20, so it must be indoors.
- Earthing: bond every rail and panel frame to the site earth with at least 6 mm² copper.
Not on the Muden quote: bring these
- 6 mm² PV cable for the return lead (about 11 m), the jumper and the run to the inverter. Measure first; 30 to 40 m was budgeted.
- Earthing conductor, lugs or bonding clips, and the connection to the earth rod.
- Roof sealant, EPDM washers, UV-rated cable ties or clips.
- Optional: 4 extra L-feet.
Commissioning
- Before closing the isolator: check polarity and measure the string's open-circuit voltage.
- Expect about 380 to 425 V in daylight. It reads lower when the panels are hot.
- About 50 V low means a panel is left out of the string.
- About 100 V low means one panel is connected backwards.
- Insulation test: if a tester is available, test + and − to earth.
- Close the isolator. Check PV1 voltage, current and power on the inverter display and in OpenEMS.
- Photos: the panel labels and serial numbers (for the warranty), the finished array, the isolator and the surge protector.
- Update this page with the as-built positions, the measured pitch and the voltage reading.
Expected output
Average kWh per day by month, unshaded, north-west face at 20° (PVGIS):
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 18.6 | 20.0 | 20.4 | 19.7 | 18.7 | 18.5 | 19.1 | 18.2 | 18.2 | 17.7 | 16.8 | 17.2 |
That is about 6,780 kWh a year. It agrees with the 5.2 peak-sun-hour assumption in the sizing re-run (about 19.5 kWh/day). Single days swing a lot with the weather. A month that comes in well below these figures points to shade or a wiring fault.
Assumptions
- Roof dimensions come from Google and Esri satellite imagery, scaled from the Google Maps scale bar, and are good to about ±0.5 m. The pitch is assumed to be 20°.
- The PVGIS figures include no tree shading.
- Sources: Golden Sun GS600N-144M datasheet; SRNE ASP 8 to 12 kW three-phase datasheet V1.0.