Skip to main content

Handling "too good to be true": explaining the Commercial RPM model

How to answer a Commercial RPM customer who thinks the offer is "too good to be true" or fears paying more later. Includes analogies that work for architects and other built-environment professionals in Uganda. Customer one-pager: Reliable Power as a Service: how it works and what you pay. Current terms: NFE Commercial Reliable Power Microgrids. Owner: Aaron Tushabe. Last reviewed 21 Nov 2026.

The short answer

"You pay the same ERA tariff you pay UEDCL today. We earn our money from the sun on your roof, not from you."

People suspect a deal is too good to be true when they can't see how the other side makes money. Show them how NFE makes money first.

Talk track

Customer's worry What to say Analogy
"How can you make money at the same price?" Solar used directly, and solar stored in the battery for the 18:00–24:00 peak, replaces grid power NFE would otherwise buy at the price it sells at. That gap is the margin. Rainwater harvesting. Someone installs a tank on your building at their own cost. You keep paying the NWSC rate; rain costs them nothing, and the gap pays for the tank.
"Why is reliability free?" The battery works every day, not only during outages. When the grid fails in the evening, it keeps doing what it was already doing. The tank is used every day, not kept for emergencies.
"Will the price creep up?" The price is the ERA Code 10.2 tariff, with taxes shown separately. NFE can't set its own rates, and there is no reliability fee. A BoQ priced against a published rates book. No new rates and no variations.
"What if equipment fails?" NFE designs, finances, owns, maintains and replaces the equipment. Battery and inverter replacement is funded from day one. A design-build-operate contract where the contractor also runs and maintains the installation.
"How do you know what we need?" Phase 1 meters the site for about 3 months before anything is sized. A site survey before the foundations are designed.
"Can we own it?" Optionally, from year 5. The buyout method is agreed at signing. Rent-to-own, with a fixed contract sum rather than open-ended variations.

Name the exceptions yourself

Bring these up before the customer finds them in the contract. Being upfront about them is what builds trust.

  • 50% minimum monthly payment. It replaces a lower bill and is never added on top. Service credits apply if NFE fails to deliver.
  • ERA tariff changes pass through, but UEDCL would have applied the same change.
  • VAT is shown separately.
  • Early termination carries a payment, like breaking a lease.
  • Buyout is optional. The price must at least clear any outstanding project debt.

Don't

  • Don't quote internal economics (IRR, CFADS, DSCR, CAPEX or financing structure). Customer-facing material leaves these out (decision of 1 Oct 2026).
  • Don't promise specifics on terms that aren't standard yet: contract term, deposit, SLA wording, tariff indexation, early-termination amount and buyout method. Say "these will be written into the contract, and we'll go through them with you before you sign."
  • Don't promise savings at the same tariff, unless the site runs a generator. Avoided diesel is where the customer saves money; otherwise the benefit is reliability at no extra cost.