Outage log

Date  Duration Reason Impact Remarks
1 September 2025 8 hours 2/3 phases with voltage too low due to a broken link, this one impacted a wider area (whole of Nansana)  all 10 customers impacted because deployment was still in progress Known to happen fairly often and could we temporarily resolved  locally with a phase selector 
6th September 2025 1 hour Meter Alarm triggered for Main house Main house only  Need to investigate reason why alarm/relay was triggered
9th September 2025 6 hours  Transmission team doing substation maintenance so they shut down the line 10/10 houses impacted.