Skip to main content

Outage log

Date  Duration ReasonImpact Remarks
1 September 2025 8 hours 2/3 phases with voltage too low due to a broken link, this one impacted a wider area (whole of Nansana)  all 10 customers impacted because deployment was still in progressKnown to happen fairly often and could we temporarily resolved  locally with a phase selector 
6th September 20251 hourMeter Alarm triggered for Main houseMain house only Need to investigate reason why alarm/relay was triggered
9th September 2025 6 hours  Transmission team doing substation maintenance so they shut down the line 10/10 houses impacted.