Advanced Search
Search Results
111 total results found
A2EI Data
Thank you for showing interest in our data and our efforts here at the A2EI! We are happy to provide you with our latest data releases from our Solar Killed the Generator Star Project in Nigeria, our clean cooking pilots, and our research into productive-use ...
Membership
Workers Founding Team Dansturn Kimbowa Hillary Arinda Aaron Tushabe Funders Danturn and Ethol Kimbowa Martha and Aaron Tushabe Hillary Arinda Customers Sezibwa Homes Samuel Kisakye Juliet N. Sezibwa Peter Ntale Wata...
NFE checkin 02/08/2025
Agenda Action items from last week Submit all outstanding expenses for Phase 1 - Dansturn Customer contact information collected - Aaron Done. Entered here and in Calin AMI Complete service cable installations - Dansturn We have an extra hom...
Co-op Resources from Startup.coop
We also encourage you to check out our free Lean Co-op course if you haven’t already and see if there are local resources within the Cooperation Works network who can continue to help you refine your vision! We have also listed advocacy, technical assistan...
NFE Mid week 08/06/2025
Agenda Site layout review Action items Review cost pf phase selectors and see if we can add them to phase 1.1- Dansturn Provide meter reference - Dansturn Reach out to our UEDCL connections - Hillary | Dansturn | Aaron
NFE Checkin 8/8/2025
Agenda Action items from Last Week Review cost of phase selectors and see if we can add them to phase 1.1- Dansturn to be shared. Provide meter reference - Dansturn This was provided Reach out to our UEDCL connections - Hillary | Danstu...
Battery as a service Provider
SLS energy based in Rwanda Cost: USD 4.40-6.48 of system capacity available per month. Also depends on the duration of the lease.
NFE / SLS Energy / Energy IoT -intro meeting
Quick summary During this meeting, Arila, Merci, Léandre, and Aaron discussed a collaboration on an open-source microgrid project in Uganda, focusing on battery storage solutions, battery-as-a-service models, and integration with open-source energy management...
NFE Checkin 03/08/2025
Agenda Reach out to our UEDCL connections - Hillary | Dansturn | Aaron Review cost of phase selectors and see if we can add them to phase 1.1- Dansturn Suggestion to power the PDU with one of the existing power sources.- Aaron Get in touch with Hopetell...
Welcome Note to Customers
Hello, This is Aaron from Nearly Free Energy. We provide reliable electricity to neighbourhoods like yours. Your landlady has agreed to work with us to bring reliable power to your neighborhood. This will be done in the a 3 phase process. Phase 1: Smart Mete...
NFE checkin August 30th 2025
Attendees Dansturn Dismas - Green Volta Engineer Aaron Agenda Going live in Sezibwa Microgrid CIUs - do we need them Notes Dismas: Cables were laid to the Main house, R2 and R3. Connection to R3 was attempted and Meter input voltage was ...
NFE Checkin - Sept 6th 2025
Going live - any blockers and questions How can we tell if UEDCL power is off? Check the gateway? Let's ask Calimeter Action items Get in touch with Dismas on going live today -Aaron Find out from Scott about how to change the low voltag...
Outage log
Date Duration Reason Impact Remarks 1 September 2025 8 hours 2/3 phases with voltage too low due to a broken link, this one impacted a wider area (whole of Nansana) all 10 customers impacted because deployment was still in progress Kno...
NFE Weekly Checkin September 13th 2025
Agenda Fundraising Updates and requests for review We are live: What next? Operation strategy Data analytics and reports: how do we take advantage of this How can we tell if UEDCL power is off? Gateway status will tell us Yaka units Re...
NFE Weekly Checkin September 19th 2025
Agenda Fundraising Updates and requests for review Game plan for Phase 2 New team members: Nickson Phase 1.1: How do we resolve phase 1 current issues Phase selector Reviewing Data from the meters/gateway Actions from previous meeting ...
Phase 1.1
Goal Install phase selectors to increase reliability when some phases have low voltage Item Specification Quantity Unit Price Amount Remarks PDU 80cm*60cm*25cm 1 900,000 900,000 We need a bigger PDU in order to fit the phase select...
NFE Mid week Checkin September 25th 2025
Sezibwa Phase 1.1 Progress updates Calinmeter Gateway issues Billing readiness Battery / Inverter evaluations updates Notes Actions Collect data for phase issues in Sezibwa - Aaron + Hillary Manage Calinmeter issues and refocus on new so...
Phase 2.0
Goal: Adding Battery Capacity. We are estimating that we need to add 15 to 25 kWh of battery capacity. We are yet to do some analysis on the consumption and outage profile for the community to determine what would be the ideal capacity.