Recently Updated Pages
NFE Checkin - August 29th 2026
Agenda Fundraising Debt/Asset financing updates - Stanbic Q3 goals - Product Goals...
Glossary
NFE Acronym Glossary This glossary consolidates acronyms used across the NFE BookStack. It covers...
Membership
Workers Founding Team Dansturn Kimbowa Hillary Arinda Aaron Tushabe Funders ...
Phase Balancing Recommendation (Sezibwa)
Recommendation for re-assigning Sezibwa's single-phase customers across the three phases of the S...
OpenEMS Backend InfluxDB Data Model and Edge-ID Collision
[!warning] Verification statusThe storage-key collision vulnerability is confirmed in source cod...
Battery Price Break-Even (Sezibwa)
Data provenance Underlying data: the aggregate meter meter_100 plus the 10 customer sub-meters, o...
Optimal Solar and Battery Allocation (Sezibwa)
Data provenance Underlying data: the aggregate meter meter_100 plus the 10 customer sub-meters, o...
Battery Arbitrage Economic Case (Sezibwa)
Data provenance Underlying data: the aggregate meter meter_100 plus the 10 customer sub-meters, o...
Solar Plus Battery Economic Case (Sezibwa)
Data provenance Underlying data: the aggregate meter meter_100 plus the 10 customer sub-meters, o...
NFE Weekly Checkin - March 21 2026
Agenda Demo for Metering 2.0 Changes Review of NFE business models: https://bookstack.nearly...
Business Models for the NFE Microgrid OS
[!info] Current working basis — August 2026Tariff: UEDCL Code 10.2, Q3 2026: Peak 666.5 / Shoul...
SRNE phase balancing: big consumers on one phase trip the inverter on battery
Problem When the site runs on battery (grid outage, typically evening or night), switching on a l...
SRNE TOU arbitrage: plan (#67)
The plan to turn on time-of-use battery arbitrage on the Sezibwa/Nansana SRNE inverter (logger i...
Inverter-monitor notifications: hardening + tuning (ADR-012)
How the NFE inverter-monitor decides what to alert on, and the 2026-08-10 hardening pass that ki...
SRNE ASP48120SH3 Safe Settings Write: design, registers, and commissioning (#53)
Purpose and scope This page documents the SRNE ASP48120SH3 safe settings write feature (story #53...
NFE metering strategy + Glen Street-EMS
Authoritative page for NFE's role in the IEEE Smart Village meshEMS / Street-EMS initiative. Com...
Metering protocols: DLMS/COSEM, OBIS, Modbus, MQTT (and NFE CHINT register map)
Traceable explainer: how metering data actually moves, where DLMS/COSEM, OBIS, Modbus, MQTT and ...
Tech Huddle - Behind the Meter Connection for each customer
How each customer is metered and controlled behind the bulk connection, in the Street-EMS design...
SRNE charge/discharge scheduling registers (self-decoded, #67)
Summary We self-decoded the SRNE ASP48120SH3 settings registers (V1.7 protocol PDF + a live read-...
NFE Checkin - August 8th 2026
Date: 8 August 2026Attendees: Aaron Tushabe, Dansturn Kimbowa, Hillary ArindaDuration: ~2 hours 5...