Community Checkins
Agendas, Meeting notes and recordings for all our meetings
Previous Meetings Recorded
NFE Checkin 10/04/2025 NFE Checkin 17/04/2025 NFE Checkin 25/04/2025 NFE Checkin 02/05/20...
NFE Checkin - 16/05/2025
Agenda Metering Evaluation review Pearl Marina Proposal Review Company tools Demos El...
NFE Checkin - 23/05/2025
Payment System Evaluation Design of Sezibwa Rentals Microgrid Need to a separate switch to...
NFE Checkin - 30/05/2025
Agenda Payment Processor demo AMI demo CalinAMI MicroPowerManager Other collabor...
NFE Checkin - 06/06/2025
Agenda AMI demo CalinAMI MicroPowerManager Other collaboration tools dashboar...
NFE Checkin - 20/06/2025
Agenda Operation Updates How to apply for Three Phase connection BOQ updates for Sezibwa R...
NFE Checkin - June 24th 2025
Action items Power bank for Gateway - Aaron Padlocks for gateway - Aaron Set up Calinmete...
NFE <> EnAccess Checkin
Attendees Aaron Tushabe - NFE Vivien - EnAccess Daniel - EnAccess Meeting link: htt...
NFE Checkin - July 4th 2025
Agenda Sezibwa rentals BOQ review Open Questions How we are funding it NFE will fund...
NFE Checkin - July 9th 2025
Agenda -
NFE Checkin 11/7/2025
Agenda Review of Last week's Action items Review of progress on PDU setup Discuss next s...
NFE Checkin 18/7/2025
Agenda Sezibwa Homes Phase 1 - Deployment Blockers New CODE 10 application - I tried apply...
NFE checkin 26/07/2025
Agenda Previous action items Provide Cert Number for Code 10 application (6890377606518) - ...
NFE <> Power for All - July 31st 2025
Had a meet and great with Joel, Alba and Sumaya from power for all. They shared plenty of quest...
NFE checkin 02/08/2025
Agenda Action items from last week Submit all outstanding expenses for Phase 1 - Dansturn C...
NFE Mid week 08/06/2025
Agenda Site layout review Action items Review cost pf phase selectors and see if we ca...
NFE Checkin 8/8/2025
Agenda Action items from Last Week Review cost of phase selectors and see if we can add the...
NFE / SLS Energy / Energy IoT -intro meeting
Quick summary During this meeting, Arila, Merci, Léandre, and Aaron discussed a collaboration on...
NFE Checkin 03/08/2025
Agenda Reach out to our UEDCL connections - Hillary | Dansturn | Aaron Review cost of phase s...
NFE checkin August 30th 2025
Attendees Dansturn Dismas - Green Volta Engineer Aaron Agenda Going live in Sezibw...
NFE Checkin - Sept 6th 2025
Going live - any blockers and questions How can we tell if UEDCL power is off? Check the g...
NFE Weekly Checkin September 13th 2025
Agenda Fundraising Updates and requests for review We are live: What next? Operation stra...
NFE Weekly Checkin September 19th 2025
Agenda Fundraising Updates and requests for review Game plan for Phase 2 New team members:...
NFE Mid week Checkin September 25th 2025
Sezibwa Phase 1.1 Progress updates Calinmeter Gateway issues Billing readiness Battery / ...
NFE weekly checkin October 11th 2025
General Updates Usage and billing for September: Battery evaluations: we have some local sup...
NFE Weekly - October 18th 2025
Previous actions Compliance and Safety inspection letter from Certified Engineer - Dansturn ...
NFE Weekly Checkin - October 25th 2025
Agenda Battery evaluation updates Fundraising Updates 100% paid up for September We have...
NFE Weekly Checkin - Nov 1st 2025
Agenda Fundraising Continues Praxis not successful Submitted D-Prize (20K) Up Next ...
NFE Weekly Checkin - Nov 15th 2025
Previous meeting action items Export Daily usage data from CalinAMI to determine maximum deman...