NFE checkin 02/08/2025
Agenda
Action items from last week
- Submit all outstanding expenses for Phase 1 - Dansturn
- Customer contact information collected - Aaron
- Complete service cable installations - Dansturn
- Schedule follow-up call with Vivien - Aaron
- Autarky (Titiana) Follow-up call - Aaron
- How to collect data from Chint three phase meter - Aaron/Dansturn
- Made some progress, it's seeming too costly to get a calin meter that will measure this load, they want to sell us more than just the meter
New items
- Fundraising updates, check the tracker
- Energy IoT and battery + inverter donations
- They have a battery (20kwh) for us but we need to ship it in from USA
- She has an inverter for us, it's an 8kw inverter though
- She will be drafting an MOU to communicate what EIoT needs out of this engagement
- Applying for an EU grant (100k to 250k Euros) with EnAccess + Another company
- Business development
- Setting up MicroPower Manager
- Still running into some issues that I am sharing with EnAccess on Discord. We will launch without it and enable it later
- Updates from Location in Nansana
- Meter should have been installed
- We are using UEDCL downstream breakers
- We will not use the customer's solido
- Safety risk if the solido is live - we need to terminate it - how?
- Calin AMI open issues
New Action items
- Submit all outstanding expenses for Phase 1 - Dansturn
- Collect National IDs for all customers
- Complete service cable installations - Dansturn
- Follow up on shipping battery and inverter to Uganda by October - Aaron